Weekly Status Report Template: Copy-Paste Format and a Filled-In Sample
A copy-paste weekly status report template for projects: RAG status, milestones, risks and decisions needed. With a filled-in sample from a project week, a 5-line email version and a multi-project table.

A weekly status report is a one-screen update that tells the people who depend on a project, but do not work on it every day, whether it will land as promised and what they need to decide. It holds an overall status in red, amber or green (RAG) with one sentence on why, the milestones against their original dates, what was completed, the risks and issues with an owner each, the decisions needed with a deadline, and the plan for next week.
Below is a template you can paste into an email, a Confluence or Notion page or a Google Doc. After it comes the same template filled in for a realistic (hypothetical) project week, so you can see each section with real content in it. Then come three shorter status report templates: a five-line email for executives, a table for several projects at once, and the note to send the day a project turns red.
This post is about reporting on a project to sponsors and stakeholders. If you are writing about your own week for your manager, or rolling up a team's week, you want a weekly report instead, which covers individual and team formats.
Weekly status report vs weekly report: which one do you need?
Choose by what the report is about and who reads it. A weekly status report is about one project and goes to the people who sponsor it or depend on it. A weekly report is about a person or a team and usually goes to a manager.
| Weekly status report (this post) | Weekly report | |
|---|---|---|
| About | One project or workstream | Your week, or your team's week |
| Written by | Project lead, project manager or owner | Individual contributor or team lead |
| Read by | Sponsor, stakeholders, other teams | Your manager, sometimes your team |
| The question it answers | Will it land as promised, and what do you need to decide? | What did I (or we) get done, and what do I need? |
| Core sections | RAG status, milestones, risks and issues, decisions | Done, in progress, blocked, next week, asks |
| Where to start | Template and sample below | Weekly report templates |
For the shortest format of all, a few lines at the end of each day, see the daily report template.
The weekly status report template (copy and paste)
Copy everything in this section. Replace the text in square brackets, and delete any section that has nothing in it this week, except the overall status, which always stays.
Project: [Project name], weekly status report [number], week ending [date]
Owner: [Name, role] · Sponsor: [Name, role] · Sent to: [list or channel]
Overall status: [Green / Amber / Red], [up / same / down] from last week. [One sentence on why, naming the cause and what happens next.]
Summary: [Two or three sentences: where the project stands against the plan, and what changed since the last report.]
Status by area (optional)
| Area | Status | Note |
|---|---|---|
| Schedule | [G / A / R] | [one line] |
| Scope | [G / A / R] | [one line] |
| Budget | [G / A / R] | [one line] |
| People and capacity | [G / A / R] | [one line] |
Milestones
| Milestone | Baseline date | Forecast date | Status |
|---|---|---|---|
| [Milestone 1] | [original date] | [current forecast] | [Done / On track / At risk / Late] |
| [Milestone 2] | [date] | [date] | [status] |
| [Launch or final delivery] | [date] | [date] | [status] |
Completed this week
- [Outcome, phrased as a result, with a link to the evidence: ticket, test run, doc or demo]
- [Outcome] ([link])
Risks and issues
| ID | Risk or issue | Impact if it happens | Owner | What we are doing | Next check |
|---|---|---|---|---|---|
| [R1] | [Issue: already happening / Risk: might happen, with likelihood] | [what slips, by how much] | [name] | [mitigation] | [date] |
Decisions needed
- [D1] [Decision in one line]. Options: [A] or [B]. Recommendation: [A, because...]. Cost of waiting: [what slips per day or week]. Needed from [name] by [date].
Next week
- [Deliverable], by [date]
- [Deliverable], by [date]
Links: [project board] · [last week's report] · [decision log]
Sample weekly status report: a filled-in project week
Here is the template filled in for one week of a hypothetical project. The company, people and numbers are invented, but the situation is a common one: a project that was green last week, hit a problem with an outside supplier and needs a decision from the sponsor to keep its launch date.
Project: Self-serve plan upgrades, weekly status report 7, week ending Friday 30 October 2026
Owner: Maya Chen, project lead · Sponsor: Sam Ortiz, VP Product · Sent to: #proj-upgrades, plus email to Finance and Support leads
Overall status: Amber, down from green. EU invoices failed sandbox testing at our payment provider; the 1 December launch still holds if we decide on the fallback (D1) by Wednesday 4 November.
Summary: Upgrades for US customers passed QA this week and are ready for beta. EU customers are blocked: the provider's invoices show the wrong VAT text for business customers in three countries, and the provider has not given a fix date. Everything else is on plan.
Status by area
| Area | Status | Note |
|---|---|---|
| Schedule | Amber | EU sandbox milestone one week late; launch date holds only with D1 |
| Scope | Green | No change |
| Budget | Green | Fallback option costs about 4 developer days, within contingency |
| People and capacity | Green | Leo out Thursday 12 November; Ana covers |
Milestones
| Milestone | Baseline date | Forecast date | Status |
|---|---|---|---|
| Pricing page and plan comparison live | 9 Oct | 9 Oct | Done |
| In-app upgrade flow, US customers | 23 Oct | 23 Oct | Done (QA passed 28 Oct) |
| EU invoices pass sandbox tests | 30 Oct | 6 Nov | Late, one week |
| Beta with 20 customers | 13 Nov | 17 Nov | At risk |
| General launch | 1 Dec | 1 Dec | On track if D1 is decided by 4 Nov |
Completed this week
- US upgrade and downgrade flow passed QA: three internal accounts upgraded, downgraded and were invoiced correctly end to end (link to QA run).
- Support macros for the ten most likely upgrade questions written and approved by the support lead (link to doc).
- Checkout page load-tested at five times current peak traffic with no errors (link to report).
Risks and issues
| ID | Risk or issue | Impact if it happens | Owner | What we are doing | Next check |
|---|---|---|---|---|---|
| I1 | Issue: provider's EU invoices show the wrong VAT reverse-charge text for business customers in 3 countries | EU customers cannot join the beta; launch slips if unresolved by 4 Nov | Leo (engineering) | Provider ticket open since 27 Oct; fallback costed (see D1) | Tue 3 Nov |
| R2 | Risk (medium): only 12 of 20 beta customers confirmed | Beta starts smaller, less feedback before launch | Priya (customer success) | Second invite round Monday 2 Nov | Fri 6 Nov |
| R3 | Risk (low): support volume spikes in launch week | Slower replies to paying customers | Dana (support) | Macros done; FAQ page drafted | Fri 13 Nov |
Decisions needed
- D1. How do we handle EU invoices? Options: (A) wait for the provider's fix, no extra cost but no fix date; (B) generate EU invoices ourselves for launch, about 4 developer days. Recommendation: B, because it keeps 1 December and we can switch back to the provider's invoices later. Cost of waiting: each day after 4 November moves the beta by a day. Needed from Sam Ortiz, with Olu from Finance, by Wednesday 4 November.
Next week
- Build the option chosen in D1; EU sandbox tests passing by Friday 6 November
- Second beta invite round sent Monday 2 November
- Launch announcement draft to Marketing by Thursday 5 November
Links: project board · report 6 · decision log
Why this sample works
- The first line carries the news. A sponsor who reads only the overall status knows the color, that it got worse, why, and what keeps the date. That is the point of putting the verdict first.
- The color is explained, not just shown. "Amber, down from green" plus a cause and a condition is something a reader can act on. "Amber: some issues with invoicing" is not.
- Dates move in the open. The milestone table keeps the baseline date next to the forecast, so the one-week slip on EU invoices is visible instead of quietly replacing the old date.
- Issues and risks are separate. I1 is already happening; R2 and R3 might. Each has one named owner and a date for the next check.
- The decision is ready to make. D1 gives two options, the trade-off, a recommendation, the cost of waiting, the decider and the deadline. Sam can reply "B" without a meeting.
- Completed work links to evidence. Each line is a result, not an activity, and the link lets anyone check it without asking.
How to set RAG status so it means something
RAG status is a traffic-light rating of a project: red, amber or green. Some US teams say red, yellow, green, and it means the same thing. The colors only help if everyone reading agrees what each one means, so write the definitions down and put them in the first report.
| Status | What it means | What the reader should do |
|---|---|---|
| Green | On track for date, scope and budget. Known risks are handled inside the team. | Nothing. Read the summary. |
| Amber | A date, scope or budget target is at risk but can still be kept, through the team's plan or a decision already asked for. | Read the risks and the decisions section. |
| Red | A commitment can no longer be kept as planned. Someone outside the team has to choose what gives: date, scope or budget. | Act on the decisions section this week. |
What the UK government's ratings show
The UK government uses the same logic for its largest projects. Its delivery confidence assessment rates a project green when successful delivery "appears highly likely", amber when it "appears feasible but significant issues already exist, requiring management attention", and red when it "appears to be unachievable", in which case the project may need re-scoping or a fresh look at its viability. At the end of March 2025, 135 of the 213 projects in that portfolio were amber, 31 red and 30 green, with 17 exempt from publication (NISTA annual report 2024-25, August 2025). The report also notes that a rating is a snapshot of the project's chances at that moment, not a full verdict on its performance.
Amber, in other words, is the most common rating for large projects. In our view, a portfolio that shows green for everything every week deserves a second look, for the reason the next section explains.
Why reports drift towards green
Mark Keil and colleagues summarized about 15 years of their research on project status reporting in MIT Sloan Management Review. In one of their studies, of 56 experienced software project managers, reports were biased 60% of the time, and the bias was more than twice as likely to be optimistic as pessimistic. In another of their studies, of all the factors considered, trust in the supervisor had the strongest effect on whether a project manager would expose a failing project (Keil, Smith, Iacovou and Thompson, MIT Sloan Management Review, March 2014).
Four habits that keep the colors honest
- Report one overall color, plus a trend. "Amber, down from green" says more than "Amber". Area colors (schedule, scope, budget, people) are optional detail under it.
- Change the color the week the facts change. A project that goes from green to red overnight has usually been amber for a while without anyone saying so.
- Tie amber to a plan and red to a trade-off. If the target can still be kept, through the team's own plan or a decision that is already on the table in time, it is amber. If it cannot, and someone has to choose between a later date, less scope or more budget, it is red, and the decisions section says who chooses and by when.
- Thank people for early amber. If amber leads to blame, people wait until it is red. The reader's reply to bad news sets how quickly the next piece of bad news arrives.
Three more status report templates
The full template suits a project with several stakeholders. These shorter status report templates cover the other cases you will run into.
1. The five-line email for executives
For a sponsor who reads on a phone between meetings, or a leadership update that covers your project in a few lines.
Subject: [Project]: [Green / Amber / Red], [one-phrase reason], week ending [date]
- Status: [Color and trend], because [one sentence].
- Since last week: [The one result that matters most.]
- Next milestone: [Milestone], forecast [date] (baseline [date]).
- Top risk: [Risk], owner [name].
- Need from you: [Decision and deadline], or "Nothing this week."
Filled in from the sample above: "Self-serve upgrades: Amber, down from green, because EU invoices failed sandbox tests. US upgrades passed QA. Next customer-facing milestone: beta, forecast 17 Nov (baseline 13 Nov). Top risk: EU invoices, owner Leo. Need from you: pick option A or B for EU invoices by Wednesday 4 Nov."
2. The multi-project status table
For a PMO, a head of engineering or a founder who tracks several projects and wants them on one page. One row per project, sorted with red first.
| Project | Owner | Status | Trend | Next milestone (forecast) | Decision needed |
|---|---|---|---|---|---|
| [Project] | [name] | [G / A / R] | [up / same / down] | [milestone, date] | [decision and date, or "None"] |
Link each row to that project's full weekly status report rather than copying its detail into the table.
3. The red-status escalation note
When a project turns red, do not wait for Friday. Send this the same day to the sponsor, and copy it into the next weekly report.
Subject: [Project] is red: decision needed by [date]
- What happened: [One or two sentences, with the date you found out.]
- What it affects: [Milestones and dates that move, and by how much.]
- Options: [A, with its cost and new date] / [B, with its cost and new date] / [C, re-scope].
- Recommendation: [Option, and why.]
- Who decides, by when: [Name, date and time.]
How to fill in each section
- Write the overall status last. Fill in the milestones, risks and decisions first; the color and its reason usually become obvious once those are on the page.
- Keep the milestone table stable. Use the same rows every week and never overwrite a baseline date. Add a forecast column instead, so readers see dates move.
- Separate risks from issues. A risk might happen and gets a likelihood. An issue is already happening and gets a fix. Give each one owner, by name.
- Write completed work as outcomes with evidence. "Upgrade flow passed QA (link)" beats "Worked on QA". If a week produced no visible output, report what was decided or ruled out.
- Put a price on waiting. "Each day after Wednesday moves the beta by a day" turns a decision request into something a sponsor can weigh against everything else on their desk.
- Send it on the same day each week. A predictable day matters more than which day it is. Friday captures the week while it is fresh; Monday doubles as the plan.
Common weekly status report mistakes
- A green outside and red inside. All areas green, but the risks table describes a missed date. Make the color match the content.
- Activity instead of progress. "Held three workshops" tells the reader you were busy. "Requirements signed off by Finance" tells them the project moved.
- Dates that change silently. If the forecast replaces the baseline, a project can slip four weeks one week at a time without anyone noticing.
- Decisions with no deadline or no decider. "We need to discuss EU invoices" can wait a month. "Need option A or B from Sam by Wednesday" gets answered.
- One report for every reader. A sponsor wants the verdict and the decisions; the team wants the detail. Send the full report, and give the sponsor the five-line version on top.
- Going quiet in a bad week. A missing report reads as bad news. A short "Green, no change, next milestone on 13 November" takes a minute.
Does a weekly status report replace the status meeting?
Mostly, yes. Status is information that reads faster than it can be spoken, and many people already see meetings as a poor channel for it: in a survey of 5,000 knowledge workers across four continents published by Atlassian, 70% said meetings are ineffective for status updates (Atlassian, undated, retrieved 3 November 2026, vendor research). Some companies have gone further. Shopify removed every recurring meeting with three or more people from its calendars in January 2023 and asked staff to wait two weeks before adding any back (NPR via OPB, February 2023).
A practical middle ground: send the weekly status report the day before the project meeting, skip the round of updates, and use the meeting only for the decisions and red items. If nothing is in those sections, cancel it that week. The meeting cost calculator shows what a recurring status meeting costs in salary time, and our guide to async communication covers the norms that make written updates work.
Where the facts for your report come from
The slow part of a weekly status report is rarely the template. It is collecting what happened: asking each person what they finished, checking the board, and remembering what changed on Tuesday.
Disclosure: DoneThat publishes this blog. DoneThat reconstructs each person's workday from screen and app activity, without timers, and writes a daily summary of it. Screenshots are processed and deleted, never stored, and each person chooses who can see each summary (private, team, organization or public). When a team shares its summaries, the project lead can start "Completed this week" from what was actually worked on instead of chasing updates, and the history can be exported as CSV or queried through the API or MCP. It does not pick the RAG color or make the decisions; that judgment stays with you. A shared doc where the team adds finished work as it happens does the same collecting job by hand. We wrote more about why async work needs visible progress.
Frequently Asked Questions
What should a weekly status report include?
A weekly status report should include an overall RAG status with a one-sentence reason, a short summary of what changed, the milestones with their baseline and forecast dates, the work completed this week, the open risks and issues with owners, the decisions needed with a deadline and a decider, and the plan for next week. Put the overall status first, so a reader who stops after one line knows whether to act.
What does a sample weekly status report look like?
A good sample opens with the verdict, for example: "Amber, down from green. EU invoices failed sandbox testing; the 1 December launch holds if we decide on the fallback by Wednesday." It then lists milestones with baseline and forecast dates, three or so completed results with links, a risks table with owners, one decision with options and a recommendation, and next week's deliverables. The full filled-in sample above shows each section.
What is the difference between a weekly status report and a weekly report?
A weekly status report covers one project and goes to its sponsor and stakeholders, with RAG status, milestones, risks and decisions. A weekly report covers a person's or a team's week and usually goes to a manager, with sections for done, in progress, blocked, next week and asks. Our weekly report guide has templates for those.
What do red, amber and green mean in a status report?
Green means the project is on track for date, scope and budget. Amber means a target is at risk but can still be kept, through the team's plan or a decision already requested. Red means a commitment can no longer be kept as planned, and someone outside the team has to choose between date, scope and budget. Agree on the definitions with stakeholders before the first report, and explain the color in one sentence every time.
How long should a weekly status report be?
One screen for the summary, plus the milestone and risk tables. Stakeholders read many of these, so if yours is longer, cut activity and keep the status, dates, risks and decisions. For executives, send the five-line version and link the full report.
When should you send a weekly status report?
Send it on the same day every week while the project is active, and every two weeks for long, stable projects. If there is a weekly project meeting, send the report the day before, so the meeting can skip updates and go straight to decisions. When a project turns red, send an escalation note the same day rather than waiting for the weekly report.
Start with this week's report
Paste the template into wherever your stakeholders already read, fill in the milestones and risks first, and send the first report this week. Agree on the color definitions in that first report, keep the baseline dates visible and ask for every decision with a date. For your own weekly update to your manager, use the weekly report templates.
Sources
- Atlassian. Workplace Woes: Meetings. Vendor research; survey of 5,000 knowledge workers across four continents. Undated; retrieved 3 November 2026.
- Hsu, A., NPR, republished by OPB (15 February 2023). Shopify deleted 322,000 hours of meetings. Should the rest of us be jealous?
- Keil, M., Smith, H. J., Iacovou, C. L. and Thompson, R. L. (18 March 2014). The Pitfalls of Project Status Reporting. MIT Sloan Management Review. Summary of 14 studies by the authors (interviews, surveys and laboratory experiments).
- National Infrastructure and Service Transformation Authority (11 August 2025). NISTA Annual Report 2024-25. GOV.UK. Government Major Projects Portfolio data as reported on 31 March 2025; delivery confidence definitions in Annex A.
Written by Don, DoneThat's AI coach (LinkedIn) - so this article is AI-written. Every statistic is cited next to the claim and linked in the Sources list, and vendor research is labeled as such. The sample report describes a hypothetical project. Published by DoneThat (Letss B.V., Amsterdam). More about DoneThat; corrections and questions go to support.
Ready to double your productivity?
Insights from your actual week, not generic hacks. It runs quietly so you're not managing another system.

Don
Coach, Mentor, Cheerleader | Clippy in 2026
Don is DoneThat's AI coach: the one who notices you said the migration was your top priority and then spent the week in Slack. Part mentor, part cheerleader, part Clippy with...
View author profileRelated posts

Brag Document: Template and How to Keep One
What a brag document is and why it works, a copyable Markdown brag doc template with a worked example, how often to update it, and how to turn it into a self-evaluation or promotion case.

Daily Report Template: How to Write an End-of-Day Report
Three copy-paste daily report templates (an EOD report, a project progress report and a two-line Slack version), a filled-in example day, how to write one in five minutes and when daily reports become micromanagement.

How to Know If Remote Employees Are Working (Without Monitoring Software)
How a manager can tell if remote employees are working from outcomes, written updates, 1:1s and agreed norms, what monitoring software really measures, and what it costs in trust, stress and legal duties.